Macdonaldtown Gasworks | Remediation
Macdonaldtown
Gasworks
Remediation
  • homeIconHome
  • Location
  • Heritage
  • Process
  • Environment
    • Dust
    • Volatiles
    • Odour
    • Noise
    • Monitoring Results
    • Stack Emission
    • Water
    • Traffic
    • Environmental Control Enclosure
  • WHS
  • Community
    • Complaints
    • Newsletters
  • Future
    Use
  • Approval &
    Stakeholders
  • Contact
    Us
Menu back  

Macdonaldtown Gasworks Remediation

Environmental remediation involves the clean up or removal of pollution or contaminants. The Macdonaldtown Gasworks Remediation began in September 2014 due to contaminated soil present on the site. Remediation involved the excavation and removal of the contaminated soil to licensed offsite facilities. The project was completed in August 2016.

RailCorp engaged Ventia to undertake the remediation of the site. Ventia is an Australian-based contractor whose project teams have experience in remediating varied and complex contaminated sites such as the former Union Carbide site in New South Wales and the former Toowoomba Gasworks site in Queensland.

  • Home
  • >
  • Home

Project Overview

The project site housed a gasworks from 1892 until 1958 which produced gas for the lighting of railway carriages and the Eveleigh Railway Workshops. The processing of coal and shale under heat and pressure to produce the gas created by-products such as tar and ash. These wastes were left on the site when the gasworks was demolished, which was common practice at the time. Over the decades however, the wastes have contaminated the site’s soil and groundwater. The contamination sources from the former gasworks infrastructure included the heating vessels known as retorts, tar and liquor tanks, coal stores, gasholders, boiler houses and purifiers.

Following an Environmental Assessment, RailCorp received approval in January 2013 from the NSW Department of Planning & Environment to remediate the site. The remediation was required under the Contaminated Land Management Act 1997, legislation administered by the NSW Environmental Protection Authority (EPA).

The Macdonaldtown Gasworks Remediation commenced in September 2014 and concluded in August 2016. It has improved the local environment by:

  • Removing contamination caused by the former gasworks operation;
  • Preserving the heritage values of the former gasworks; and
  • Improving biodiversity via the revegetation of the western portion of the site with locally native species.

The main contaminants of concern at the site were polycyclic aromatic hydrocarbons (PAHs, including benzo(a)pyrene and naphthalene), total petroleum hydrocarbons (TPH), benzene, toluene, ethylbenzene and xylenes (BTEX) and small fragments of bonded, non-friable asbestos. Elevated concentrations of heavy metals had also been identified in groundwater.

A thorough pre-project assessment found that the risk to the community from contamination at the site was negligible. The contaminants at the site were however slowly leaching into groundwater and over time migrating towards the south-east (away from Burren St). The remediation will prevent this occurring in the future.

The remediation plan involved excavating the impacted material on the site to the extent practicable. The majority of the material was disposed of offsite to a licensed landfill. The most impacted, such as the tarry wastes, were treated offsite by cement stabilisation before landfill emplacement. Some lesser impacted material, which met specific criteria, was reinstated on the site at depth. When there were heritage or geotechnical constraints, impacted material was managed in-situ. This strategy was endorsed by a NSW EPA-Accredited Site Auditor.

Impact on train operations

The Macdonaldtown Gasworks Remediation was visible to Illawarra Rail Corridor commuters and also partially visible from the Macdonaldtown Station platform, however the work had no impact on the operation of trains in the area.

PROJECT MILESTONES  (click for details) 

Planning Approval
December 19, 2014
Offsite Treatment Trials
December 19, 2014
Environmental Monitoring Commencement
December 19, 2014
Site Establishment
December 19, 2014
Construction of Water Treatment Plant (WTP)
December 22, 2014
Installation of Underground Retaining Walls
December 22, 2014
Construction of temporary Environmental Control Enclosure (ECE)
December 22, 2014
Construction of Emission Control System (ECS) for the ECE
December 22, 2014
Commissioning of the ECE, ECS and WTP
December 22, 2014
Full Scale Remediation (Excavation)
December 22, 2014
Reinstatement of Excavated Area with Clean Material
December 22, 2014
Heritage-Listed Gasholder Restoration
December 22, 2014
Replanting with Native Trees and Shrubs
December 22, 2014
Demobilisation and Completion
December 22, 2014

Contact: Phone: 1800 009 414 Email: macdonaldtownremediation@ventia.com.au

Macdonaldtown Gasworks | Remediation
  • © Ventia 2015. Website by iNerds
  • PRIVACY STATEMENT
  • LEGAL DISCLAIMER
footerMenu